The report, completed by the Bechtel Corp. about 18 months before the project was shut down in July, also notes strained relationships between the project’s contractors, as well as a lack of shared vision and accountability among the major companies involved.
Bechtel’s report, which senior partner SCE&G did not want released, might answer questions from lawmakers about what went wrong with the project. Many lawmakers want to know whether the fiasco could have been prevented.
Cayce-based SCE&G and state-owned Santee Cooper spent nine years and $9 billion on the Fairfield County project before pulling the plug July 31. Ratepayers at both companies have been charged at least $2 billion for two nuclear reactors that won’t be completed. The utilities have said rising costs, construction delays and the bankruptcy of chief contractor Westinghouse led them to walk away……..
The Bechtel report cited “significant issues” facing the project that needed addressing.
Among the problems, the report says, was that plans and schedules for the project did not reflect actual circumstances; the construction contract did not appear to be serving Santee Cooper, SCE&G or Westinghouse well; and construction designs often were “not constructable,” which caused significant changes and delays.
Construction modules, built off site and touted as a way to ensure the project’s success, were a “detriment to the project progress and consequently the budget,” Bechtel wrote.
A key finding in the report addresses the utilities’ plan to use the AP 1000 reactor, a technology that had not been used in U.S. nuclear plants before. The report said challenges were to be expected because of the reactor type and because no nuclear plants had been built in the U.S. in decades. But it also said the V.C. Summer project “suffers from various fundamental” contract and management problems that needed resolution for the effort to succeed.
The report said contractors had not been transparent or accurate to the utilities about the project’s progress, and the utilities did not have an appropriate project team to assess or verify those contractors’ progress reports…..
Investor-owned SCE&G did not want the report released. In a Sunday letter to McMaster, the utility pleaded with the governor to keep the report confidential if Santee Cooper, the project’s minority owner, gave it to him.
If released, the report could hurt SCE&G in lawsuits, the company said. The letter also said releasing the document could hurt SCE&G and Santee Cooper in their efforts to recover “potentially billions” of dollars from Westinghouse.
Monday’s release follows two weeks of efforts by lawmakers to obtain the Bechtel report…….http://www.thestate.com/news/local/article171238277.html